The power of Loviisa power plant unit 2 has been reduced to 50% due to a turbine failure. Unit 2 is estimated to reach full power during Monday evening October 16, 2017.
The Unit 1 is in normal production.
The situation does not endanger people, environment or the power plant.
Further information:
Anssi Laakso, Manager, Plant lifetime management and Maintenance unit, tel. +358 50 455 4063